A project manager tracks the work of team members using a network logicdiagram. Which effect will th

Need your ASSIGNMENT done? Use our paper writing service to score better and meet your deadline.


Order a Similar Paper Order a Different Paper

A project manager tracks the work of team members using a network logicdiagram. Which effect will the presence of an actual finish date have on thecalculation of float for the finished activity?168o Finished activities have only float left when they have been completed onschedule.o Calculating free float and total float is generally not reasonable for finishedactivities.o When an activity has been finished, total float gets often converted to becomefree float.o When an activity has been finished, float gets often converted to becomeslack.